Data centre electrical design studies
Power system studies for mission-critical data centres across the UK, from RIBA Stage 3 design development to commissioning and handover. We model the HV and LV network in ETAP and test N+1, 2N and 2N+1 designs in normal operation, maintenance and failure.
Every study, across every operating case.
Short circuit analysis
Maximum and minimum fault currents for utility outages, generator operation and alternative supplies. We confirm every device can withstand and break the fault, and the results feed the protection design.
Load flow analysis
Loading and voltage in normal, maintenance and failure conditions. We check that when the A path is lost, the B path carries the transferred load without overloading anything critical.
Protection coordination and relay settings
Settings built from your protection philosophy: overcurrent, earth fault, transformer differential, restricted earth fault, busbar protection and inrush restraint. The nearest device clears the fault and critical loads stay on.
Arc flash risk assessment and labelling
Incident energy and arc flash boundaries across operating and failure cases, PPE selection, mitigation measures, and a warning label for each piece of equipment.
Cable sizing and thermal analysis
LV and MV cables checked for current rating, voltage drop and fault withstand, with Neher–McGrath thermal analysis of the installation, soil and grouping for the higher loading of redundant operation.
Harmonic analysis and power quality
Voltage and current distortion across LV distribution and at the MV point of common coupling, frequency scans for resonance, and filter design where needed to meet network operator limits.
Earthing system studies
Earth potential rise, touch and step voltages, and fault current paths for HV and LV installations, to support a safe earthing design.
ETAP modelling and commissioning support
One ETAP model, kept current with design changes, manufacturer data and installed equipment. At Stage 5 we validate it, finalise settings and labels, and support energisation and handover.
Four studies, one model.
Choose a case to see the result.
Arc flash and shock hazard. Appropriate PPE required.
- Incident energy
- 7.9 cal/cm²
- Working distance
- 455 mm
- Arc flash boundary
- 1.4 m
- PPE category
- 2
- Nominal voltage
- 400 V
- Limited approach
- 1.0 m
- Stage 3Design development
- Typical data
- Fault levels and ratings
- Outline protection
- Stage 4Technical design
- Manufacturer data
- Relay settings and cable sizes
- Arc flash categories
- Stage 5Commissioning
- Installed equipment data
- Final settings and labels
- Model handed over
When you need it.
- Stage 3. The design is taking shape, and fault levels and equipment ratings need confirming.
- Stage 4. Protection settings, cable sizes and arc flash categories must be fixed before procurement and installation.
- Stage 5. The installed equipment differs from the design, and the model, settings and labels must match it before energisation.
- The design is redundant (N+1, 2N or 2N+1), so every maintenance or failure case moves load onto what is left.
Four studies, one model.
Choose a case to see the result.
Arc flash and shock hazard. Appropriate PPE required.
- Incident energy
- 7.9 cal/cm²
- Working distance
- 455 mm
- Arc flash boundary
- 1.4 m
- PPE category
- 2
- Nominal voltage
- 400 V
- Limited approach
- 1.0 m
- Stage 3Design development
- Typical data
- Fault levels and ratings
- Outline protection
- Stage 4Technical design
- Manufacturer data
- Relay settings and cable sizes
- Arc flash categories
- Stage 5Commissioning
- Installed equipment data
- Final settings and labels
- Model handed over
How we run it.
- 01
Agree
Architecture, protection philosophy, and the operating and failure cases.
- 02
Model
ETAP model of the HV and LV network, generators, UPS and loads.
- 03
Scenarios
Normal, maintenance, equipment failure and alternative supplies.
- 04
Study
The eight studies, each run across the governing cases.
- 05
Hand over
Settings, labels, reports and the as-installed model.
Every scenario through every study.
- ETAPShort circuit, load flow, protection, arc flash, harmonics
- Cable thermal analysisNeher–McGrath method
- Earthing analysisEarth potential rise, touch and step voltages
Maintenance (one path out) · Arc flashWith one path out, a fault on board B reached 11 cal/cm². A maintenance mode switch brings it under 8.A or B path failure · Load flowWhen path A fails, transformer B runs at 108%. A larger rating fixes it.Utility at minimum fault level · ProtectionAt the utility’s minimum fault level the incomer relay tripped too slowly. A second setting group covers it.Future expansion · Cable sizingThe future hall pushes one feeder past its rating. One size up now saves a replacement later.
What you get.
- ModelThe ETAP model, updated to the installed equipment for handover
- SettingsRelay settings schedules and coordination curves
- LabelsArc flash labels and a PPE schedule for every piece of equipment
- ReportsShort circuit, load flow, protection, arc flash, cable, harmonic and earthing reports
How we check it
Every conclusion traces back to a validated model and a documented scenario. We record tool versions, model sources and assumptions, so the work can be rerun and challenged.
Questions engineers ask.
Which RIBA stages do you support?
Do you only work in ETAP?
Do you cover 2N and 2N+1 designs?
Have a study like this coming up?